MIL-STD-881C WhitepaperBack to the full Whitepaper
Appendix D: Ordnance Systems
Download full PDFAppendix D: Ordnance Systems
APPENDIX D: ORDNANCE SYSTEMS WORK BREAKDOWN STRUCTURE AND DEFINITIONS D.1 SCOPE
This appendix provides the Work Breakdown Structure and Definitions for the munition and launch system. Definitions for WBS elements common to the ordnance system and all other defense materiel items are given in Appendix L: Common Elements, Work Breakdown Structure and Definitions.
D.2 APPLICABLE DOCUMENTS
D.2.1 Non-Government publications. The following documents form a part of this document to the extent specified herein.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI/IEEE STD 610.12-1990 (R2002), Standard Glossary of Software Engineering Terminology
ANSI Standards can be found online at:
http://webstore.ansi.org
ANSI Customer Service 25 W 43rd Street, 4th Floor New York, NY, 10036
or
The Institute of Electrical and Electronics Engineers, Inc. (IEEE) Operations Center 445 Hoes Lane Piscataway, NJ 08854-4141 www.ieee.org
D.3 WORK BREAKDOWN STRUCTURE LEVELS
- 1.0Ordnance System
- 1.1Munition
- 1.1.1Airframe
- 1.1.1.1Airframe Integration, Assembly, Test and Checkout
- 1.1.1.2Primary Structure
- 1.1.1.3Secondary Structure
- 1.1.1.4Aero-Structures
- 1.1.1.5Other Airframe Components 1…n (Specify)
- 1.1.2Propulsion
- 1.1.2.1Propulsion Integration, Assembly, Test and Checkout
- 1.1.2.2Motor/Engine
- 1.1.2.3Fuel Management
- 1.1.2.4Arm/Fire Device
- 1.1.2.5Propulsion Software Release 1…n
- 1.1.2.6Other Propulsion Subsystems 1…n (Specify)
- 1.1.3Power and Distribution
- 1.1.3.1Power and Distribution Integration, Assembly, Test and Checkout
- 1.1.3.2Primary Power
- 1.1.3.3Power Conditioning Electronics
- 1.1.3.4Distribution Harnesses
- 1.1.3.5Power and Distribution Software Release 1…n
- 1.1.3.6Other Power and Distribution Subsystems 1…n
- 1.1.4Guidance
- 1.1.4.1Guidance Integration, Assembly, Test and Checkout
- 1.1.4.2Dome Assembly
- 1.1.4.3Seeker Assemblies
- 1.1.4.4Guidance Software Release 1…n
- 1.1.4.5Other Guidance Subsystems 1…n (Specify)
- 1.1.5Navigation
- 1.1.5.1Navigation, Integration, Assembly, Test and Checkout
- 1.1.5.2Sensor Assemblies
- 1.1.5.3Navigation Software Release 1…n
- 1.1.5.4Other Navigation Subsystems 1…n (Specify)
- 1.1.6Controls
- 1.1.6.1Controls Integration, Assembly, Test and Checkout
- 1.1.6.2Primary Structure
- 1.1.6.3Fin/Canard Deployment System
- 1.1.6.4Actuators
- 1.1.6.5Control Power
- 1.1.6.6Controls Software Release 1…n
- 1.1.6.7Other Controls Subsystems 1…n (Specify)
- 1.1.7Communications
- 1.1.7.1Communications Integration, Assembly, Test and Checkout
- 1.1.7.2Antenna Assembly
- 1.1.7.3Communications Software Release 1…n
- 1.1.7.4Other Communications Subsystems 1…n (Specify)
- 1.1.8Payload
- 1.1.8.1Payload Integration, Assembly, Test and Checkout
- 1.1.8.2Target Defeat Mechanism
- 1.1.8.3Target Detection Device
- 1.1.8.4Fuze
- 1.1.8.5Payload Software Release 1…n
- 1.1.8.6Other Payload Subsystems 1…n (Specify)
- 1.1.9On Board Test Equipment
- 1.1.10On Board Training Equipment
- 1.1.11Auxiliary Equipment
- 1.1.12Munition Software Release 1…n
- 1.1.13Munition Integration, Assembly, Test and Checkout
- 1.1.1Airframe
- 1.2Encasement Device
- 1.2.1Encasement Device Integration, Assembly, Test and Checkout
- 1.2.2Encasement Device Structure
- 1.2.3Encasement Device Software Release 1…n
- 1.2.4Other Encasement Device Subsystems 1…n (Specify)
- 1.3Launch System
- 1.3.1Launch System Integration, Assembly, Test and Checkout
- 1.3.2Launcher
- 1.3.3Carriage
- 1.3.4Fire Control
- 1.3.5Ready Magazine
- 1.3.6Adapter Kits
- 1.3.7Launch System Software Release 1…n
- 1.3.8Other Launch System 1…n
- 1.4Ordnance System Software Release 1…n
- 1.5Ordnance System Integration, Assembly, Test and Checkout
- 1.6System Engineering
- 1.7Program Management
- 1.8System Test and Evaluation
- 1.8.1Development Test and Evaluation
- 1.8.2Operational Test and Evaluation
- 1.8.3Mock-ups / System Integration Labs (SILs)
- 1.8.4Test and Evaluation Support
- 1.8.5Test Facilities
- 1.9Training
- 1.9.1Equipment
- 1.9.2Services
- 1.9.3Facilities
- 1.10Data
- 1.10.1Technical Publications
- 1.10.2Engineering Data
- 1.10.3Management Data
- 1.10.4Support Data
- 1.10.5Data Depository
- 1.11Peculiar Support Equipment
- 1.11.1Test and Measurement Equipment
- 1.11.2Support and Handling Equipment
- 1.12Common Support Equipment
- 1.12.1Test and Measurement Equipment
- 1.12.2Support and Handling Equipment
- 1.13Operational/Site Activation
- 1.13.1System Assembly, Installation and Checkout on Site
- 1.13.2Contractor Technical Support
- 1.13.3Site Construction
- 1.13.4Site/Ship/Vehicle Conversion
- 1.13.5Sustainment/Interim Contractor Support
- 1.14Industrial Facilities
- 1.14.1Construction/Conversion/Expansion
- 1.14.2Equipment Acquisition or Modernization
- 1.14.3Maintenance (Industrial Facilities)
- 1.15Initial Spares and Repair Parts
- 1.1Munition
D.3.1 Application of Common WBS Elements (Appendix L). WBS elements that are common (i.e., Integration, Assembly, Test and Checkout; Systems Engineering; Program Management; System Test and Evaluation; Training; and Data) should be applied to the appropriate levels within the WBS for which they support. For example, if Systems Engineering is required to support a Level 3 WBS element, the Systems Engineering WBS element would appear at Level 4 of the WBS under the Level 3 element it supports.
D.3.2 Key Principles in Constructing a WBS. In the appendices of MIL-STD-881C, the WBS is defined to Level 3 of that structure and in some cases Level 4 or 5. In order to ensure consistency across all systems and developers, WBS elements in the appendices are extended to levels 4 and 5.
- 1) The reporting level of the WBS is typically at Level 3 except for those items considered high cost, high risk, or high technical interest. For those elements, extension of the WBS to lower levels is necessary to get needed visibility, but only for those elements. Not all WBS elements should be extended to the lowest level. In addition, for each system being defined only those WBS elements that define the system shall be used. The purpose of going below level 3 within the appendix is to ensure that the higher level elements include the proper lower level elements and when required to report at a lower level, those elements at level 4 or 5 are consistent across all systems and developers.
- 2) In each of the appendices, an element entitled “Other” is available to provide flexibility within the WBS for new or additional WBS elements that are not identified or defined in the Standard. These “other” elements would be used if, for example, a new subsystem or modified subsystem is defined and it does not currently appear in the appendices of MIL-STD-881C.
- 3) A key to WBS development is the principle that if you can associate the WBS element with the element it supports, it should be included within that element. This is called the 100% rule, which states the next level of decomposition of a WBS element (child level) must represent 100% of the work applicable to the next higher level (parent level). For example, the parent level WBS (radar system) has three child elements – transmitter, antenna, and receiver. If the program manager decides he/she wants more visibility into the transmitter subsystem and pulls it out of the radar system and makes it a level equal to the radar, it distorts the effort and resources that are required to complete that radar system because it assumes the transmitter is not included (i.e., a child element to the radar is now missing within the WBS structure).
- 4) In some cases, items cannot be specifically associated with the element they support. For example, software is a critical element of that transmitter subsystem. Under normal circumstances, software would be the child level to the parent level transmitter. However, depending on how software is developed, the software may include more functionality than just for the transmitter subsystem. It may include functionality for the receiver as well. In this case the software cannot be associated with the specific elements they support, due to an inability to determine the effort for each functionality developed. Therefore, it is appropriate to associate that software to the next highest level (radar system) of the WBS. It is still included as a part of the radar system at the child level, but we are not trying to allocate effort across multiple WBS elements where we are unable to determine what level of support each gets.
- 5) Intelligence (Intel) efforts (security, threat, mission data) are often considered late in the acquisition cycle, even after contract award. Identifying where Intel is needed reduces risk and affords a much better opportunity to manage cost, schedule, and performance. The WBS Standard portrays systems in a product-oriented WBS, identifying and considering potential intelligence information and costs using the existing Component cost estimating processes.
D.3.3 Numbering of the WBS. In each appendix, the work breakdown structure for that commodity has been numbered for reporting purposes only. The purpose for the numbering is to provide a consistent approach to identifying and managing the WBS across like systems regardless of vendor or service. The numbering system is numeric; however, several unique issues arise across appendices which require the numbering system to be modified to accommodate the anomalies.
D.3.3.1. “Other” WBS Elements. All appendices contain a WBS element titled as “Other” at the subsystem, element (product) levels that are restricted for products that have not been envisioned or predicted within the defined WBS elements in the Appendix. If it is determined that the “other” WBS is not needed, this element and assigned WBS number should be deleted and not used in the WBS. If it is determined that the “other” element is needed, then each element must be defined and the word “other” replaced by the newly defined WBS element using the assigned WBS number from the appropriate appendix. The newly defined element must be approved by the Government Program Manager and the representative contracting officer.
D.3.3.2 (1…n) WBS Element Definitions. Several appendices identify WBS elements with (1…n) or similar to denote that one or more of that type of item may be used. Where this structure occurs, the parent WBS (e.g., 1…n) shall be decomposed to the next level and then each child WBS use the appropriate WBS title for each element as well as the WBS numbering identification. For example, if a missile system has multiple propulsion subsystems, each Propulsion Subsystem (1…n) shall have a WBS name designation (for example, “Solid Rocket Motor”), and the element Propulsion Subsystem 1 would be at the child level of the parent WBS element (Propulsion Subsystem 1…n) as would Propulsion Subsystem 2 (for example, “Liquid Rocket Engine”), and so forth. Each WBS should be detailed down to the element’s lower level (as defined in the appendices) whenever possible, and assigned the next available WBS number in sequence according to the parent child relationship as shown below.
- 1.1.2. Propulsion Subsystem (1…n)
- 1.1.2.1. Solid Rocket Motor
- 1.1.2.2. Liquid Rocket Engine
- 1.1.2.3. Backup Rocket Motor
D.4 DEFINITIONS
D.4.1 Ordnance System. The complex of hardware, software, data, services, and facilities required to develop and produce the capability for applying munitions to a target.
D.4.2 Munition. Historically, munitions were unguided weapons unpowered after leaving its launching device that has as its purpose the destruction of some object or target. The term includes, but is not limited to, such items as ammunition, projectiles, mines, bombs, rockets, mortars, depth charges and torpedoes. If guidance and control components are added to munitions to increase accuracy those modified systems are still classified as munitions. Specific examples of munitions include, but are not limited to: Excalibur, JSOW, MRM, Paveway, SDB I, SDB II. This WBS element includes the design, development, and production of complete units (i.e., the prototype or operationally configured units, which satisfy the requirements of their applicable specifications, regardless of end use) and is comprised of the sub elements listed below.
D.4.2.1 Airframe. This element comprises the structural framework that provides the aerodynamic shape, mounting surfaces and environmental protection for the munition components, which are not directly applicable to other specific Level 3 munition subsystems.
- Includes, for example:
- a. Wings and fins that provide aerodynamic flight control in response to electro-mechanical signals and are attached to the munition body
- b. Structural body assemblies including the structure, covers, skins, adhesives, and fairings not directly applicable to any other Level 3 munition subsystem
- c. Protection devices for stressing environmental conditions such as thermal protection system or rain erosion that are not directly applicable to other Level 3 munition subsystems
D.4.2.1.1 Airframe Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 4 elements below into their Level 3 element, Airframe.
D.4.2.1.2 Primary Structure. This element comprises the structural framework that provides for load carry hardware such as the air carry system, interfaces to loading and launching devices, and other hard points needed to protect the munition from environmental induced loads.
D.4.2.1.3 Secondary Structure. This element comprises the secondary hardware needed to maintain aerodynamic shapes, interfaces between other subsystems, fuel tanks, protection subsystems such as a Thermal Protection System (TPS), and other structure not directly associated with the primary structure or other Level 3 subsystems.
D.4.2.1.4 Aero – Structures. This element comprises the hardware needed for aerodynamic flight effects.
- Includes, for example:
- a. Wings, fins, canards, stability systems, and inlets for air breathing propulsion
D.4.2.1.5 Other Airframe Components 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
D.4.2.2 Propulsion. The element comprises the equipment integral to the munition, which provides supplemental forces post launch to propel the munition from its launch position to the target or to assist in countering the forces of drag (i.e., base bleed). The equipment may employ solid rocket motor or air-breathing technologies.
D.4.2.2.1 Propulsion System Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 4 elements below into their Level 3 element, Propulsion System. For example, this element includes those structural elements that transfer the thrust loads or provide the primary path for vehicle loads through the propulsion system such as forward and aft skirts and/or interstages or other components through which the propulsion system is attached to the munition and transfers primary loads. In addition it includes the hardware and secondary structure to provide interfaces to other elements such as raceways, connectors, cutouts, access doors, etc. or any other hardware that interfaces with other elements of the munition except for primary structural elements.
D.4.2.2.2 Motor/Engine (Specify). The structure (integral to the propulsion system), propellant, controls, instrumentation, and all other installed subsystem equipment integral to the rocket motor or engine as an entity within itself.
- Includes, for example:
- a. Rocket Motor. This element is applicable to a solid propulsion system and consists of the thrust producing component in which solid propellant, made up of fuel and oxidizer, is combusted and expelled through a nozzle. It includes the pressure vessel, an igniter, internal insulation, solid propellant and a nozzle. If applicable it includes the functionality to move the nozzle or a portion of the nozzle but not the actuation system to cause that movement.
- b. Air Breathing Engine. This element is applicable to an air breathing propulsion system in which a stream of air is supplied to the engine along with a liquid fuel. The engine operates to mix and combust the air and fuel and to expel the products through a nozzle to produce thrust. It includes all the turbines, compressors, injectors, etc. to act on the air and fuel from the inlet to the engine through the exhaust from the engine. It does not include aerodynamic inlets on the munition to deliver air to the engine.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.2.3 Fuel Management. All of the tanks, lines, pressurization system and/or pressure control, pumps, valves, etc. to deliver the fuel and oxidizer to the engine at the required conditions.
D.4.2.2.4 Arm/Fire Devices. Hardware to arm, disarm and initiate operation of the propulsion system.
D.4.2.2.5 Propulsion Software Release 1…n. All propulsion subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.2.6 Other Propulsion Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.3 Power and Distribution. This element comprises prime power and distribution for the munition.
D.4.2.3.1 Power and Distribution Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the above Level 4 elements into their Level 3 element, Power and Distribution.
D.4.2.3.2 Primary Power. This element comprises primary power for the munition.
- Excludes, for example:
- a. Batteries that may be integral to other Level 3 elements.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.3.3 Power Conditioning Electronics. This element comprises prime power conditioning electronics. It excludes power conditioning integral to other Level 3 elements.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.3.4 Distribution Harness. This element comprises prime power distribution harnesses.
- Excludes, for example:
- a. Harnessing integral to other Level 3 elements.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.3.5 Power and Distribution Software Release 1…n. All power and distribution subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.3.6 Other Power and Distribution Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.4 Guidance. Guidance is the process of maneuvering the munition to engage the intended target. This WBS element is the compliment of hardware, software and equipment for target detection, signal processing, implementation of guidance laws and generation of guidance commands.
- Excludes, for example:
- a. Navigation
- b. Control
D.4.2.4.1 Guidance Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 4 elements below into their Level 3 element, Guidance.
D.4.2.4.2 Dome Assembly. Windows, domes or radomes, and associated retention mechanisms, to cover the seeker(s) apertures used for target detection and is suitable to support seeker functionality. Contingent upon the design, this may be included within the Seeker Assemblies WBS element.
D.4.2.4.3 Seeker Assemblies. This element comprises the sensors (RF, EO, SAL, etc., as applicable), sensor electronics, gimbal assembly, on-gimbal electronics and integral structure(s), which constitutes the Seeker Assembly.
- Includes, for example:
- a. Radio frequency (RF), electro optical (EO), and semi-active laser (SAL) sensors
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.4.4 Guidance Software Release 1…n. All guidance subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.4.5 Other Guidance Subsystems 1…n (Specify). This element should be replaced with other product- oriented guidance subsystems that are either not listed above or that cannot be categorized into one of the above elements. Each additional element is to be clearly identified and defined.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.5 Navigation. The compliment of hardware, software and equipment to measure or determine body angles and /or body linear motion and generation of navigation commands.
- Excludes, for example:
- a. Guidance
- b. Control
D.4.2.5.1 Navigation Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout the Level 4 elements below into their Level 3 element, Navigation.
D.4.2.5.2 Sensor Assemblies. Hardware that provides data for determination of munition location and orientation.
- Includes, for example:
- a. Global Positioning System (GPS) receiver and antenna
- b. Inertial sensors
- c. Altimeter
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.5.3 Navigation Software Release 1…n. All navigation subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.5.4 Other Navigation Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.6 Controls. The hardware, software and equipment for controlling the motion of the munition from launch to impact.
- Includes, for example:
- a. Control devices for canard, wing, tail, etc.
- b. Thrust vector / jet van
- c. Explosive charge / lateral thrusters
- Excludes, for example:
- a. the control surfaces themselves (such as canards, wings, tails, etc.) included in the Airframe element
D.4.2.6.1 Controls Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 4 elements below into their Level 3 element, Controls.
D.4.2.6.2 Primary Structure. The structural framework not part of the Airframe element.
D.4.2.6.3 Fin/Canard Deployment System. The hardware for fin/canard deployment.
D.4.2.6.4 Actuators. The hardware for actuation to include motors and servos.
D.4.2.6.5 Control Power. This element comprises power for the control element.
- Excludes, for example:
- a. Central power sources included in the Power and Distribution WBS element
D.4.2.6.6 Controls Software Release 1…n. All controls subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.6.7 Other Control Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic/ Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.7 Communication. This data link equipment to enable communications between the munition and an external entity (or entities). Data links can be either receive only or send only (one-way) or bidirectional (two way).
- Includes, for example:
- a. Data transmission and reception for networking, command and control, battle space awareness, and air traffic management enabling the munition to be a node in the net
D.4.2.7.1 Communications Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the =Level 4 elements below into their Level 3 element, Communication.
D.4.2.7.2 Antenna Assembly. The hardware comprising the Antenna Assembly or Assemblies.
D.4.2.7.3 Communication Software Release 1…n. All communication subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.7.4 Other Communications Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.8 Payload. The Target Defeat Mechanism (TDM) and its support assemblies. Normally, payload consists only of the TDM and its associated target detection, arming and fuzing equipment. However, with complex munitions containing submunitions, the payload subsystem may mimic the larger system by having its own guidance and control, fuze, safe-arm, and propulsion. In multi-mission or adaptable payloads there may be a communication device that provides data to payload for output yield, real-time directions for aimable capabilities or layer-counting type applications.
D.4.2.8.1 Payload Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 4 elements below into their Level 3 element, Payload.
D.4.2.8.2 Target Defeat Mechanism. The hardware and software that produce(s) the desired effect on the target. TDMs include, but are not limited to, conventional high explosives (explosive outputs of blast, fragmentation, and penetrator-forming), directed energy devices, kinetic energy devices, dispensed submunitions or others.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.8.3 Target Detection Device (TDD). The hardware and software that detects and signals the presence of a target. TDDs include, but are not limited to, contact sensors (make or break electronics), EO or RF based proximity sensors and necessary hardware and software for signal processing.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the munition is excluded.
D.4.2.8.4 Fuze. The equipment in the munition that controls the capability of initiating the TDM (e.g., mechanical, hydrostatic, inertial, counters, and timers). It includes the hardware and software for the Safe, Arm and Fire (SAF) function; sensors and algorithms, if applicable, to enable “smart fuzing”; and the hardware and software associated with the firing train.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.8.5 Payload Software Release 1…n. All payload subsystem software not associated with a specific Level 4 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.8.6 Other Payload Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 4 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.9 On Board Test Equipment. This element comprises the payload that is interchangeable with the live warhead and suitable for development or operational testing in a free flight (post launch) environment.
- Includes, for example:
- a. Recovery systems
- b. Special instrumentation
- c. Telemetry equipment
- d. Flight termination equipment, etc., suitable for a launch and free flight environment.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.10 On Board Training Equipment. This element comprises the payload that is interchangeable with the live warhead and suitable for testing in a non-launch environment. Includes, for example, special instrumentation, telemetry equipment, etc., suitable for a non-launch environment.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.11 Auxiliary Equipment. This element comprises the complex of additional external equipment generally excluded from other specific Level 3 elements.
- Includes, for example:
- a. Environmental control, safety and protective subsystems, destruct systems, etc., if these were not accounted for in other WBS elements
- b. Equipment of a single purpose and function, which is necessary for accomplishing the assigned mission
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test, and checkout of these elements into the Munition is excluded.
D.4.2.12 Munition Software Release 1…n. All munition software not associated with a specific Level 3 or 4 element.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.2.13 Munitions Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 3 elements below into their Level 2 element, Munitions.
D.4.3 Encasement Device. The hardware and software associated with the Munition Canister or Encasement device.
D.4.3.1 Encasement Device Integration, Assembly, Test, and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the above Level 3 elements into their Level 2 element, Encasement Device.
D.4.3.2 Encasement Device Structure. This element comprises the primary structure of the canister or encasement device.
D.4.3.3 Encasement Software Release 1…n. All Encasement software not associated with a specific Level 3 element above.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.3.4 Other Encasement Device Subsystems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 3 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 2 element.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test, and checkout of these elements into the Encasement Device element is excluded.
D.4.4 Launch System. The equipment (hardware/software) for controlling or sending forth the munitions on a desired course or trajectory.
- Includes, for example:
- a. Rifles, artillery pieces, naval guns, mortar cannons, machine guns, and the equipment for launching torpedoes and rockets or dropping bombs (e.g., the launcher, fire control equipment, and the ready magazine).
- b. All effort associated with the design, development, and production of complete units (i.e., the prototype or operationally configured units, which satisfy the requirements of their applicable specifications, regardless of end use).
D.4.4.1 Launch System Integration, Assembly, Test and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the Level 3 elements below into their Level 2 element, Launch System.
- D.4.4.2 Launcher. The structural device designed to support and hold munitions in position for firing or release. Includes, for example:
- a. Suspension and release systems, rail, rocket pods, mine racks or dispensers, and torpedo tubes and other devices which support, suspend, or encase the munition for firing. These other devices would be in addition to any encasement, if applicable, integral to a munition.
- b. (For guns and artillery) tubes, recoil assemblies, breech mechanisms, mounts, and rifle stocks
D.4.4.3 Carriage. The primary equipment (hardware/software), which serves as a platform to accommodate the other Level 3 elements and provides mobility to the complete launch system (e.g., T-frame, hull/chassis, wheels, tires, tubes, brakes, hydraulics, and secondary power batteries/generators), which are an integral part of the carriage itself and not directly a part of other Level 4 elements.
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test and checkout of these elements into the Launch System is excluded.
D.4.4.4 Fire Control. The equipment (hardware/software) for controlling the direction, volume, and time of fire or release of munitions through the use of electrical, electronic, optical, or mechanical systems, devices or aids.
- Includes, for example:
- a. (For rifles and small arms) sighting devices and trigger mechanisms
- b. (For artillery, naval guns, and heavy mortars) aiming mechanisms in traverse and elevation, radar and other sensors, computers and other equipment for performing fire control computations
- c. (For air-dropped munitions) gunsights, intervalometers, and other sensor and computational devices for controlling the release of the munitions
- d. (For torpedoes) sonar and other sensors, computers, control consoles, and devices for presetting torpedo speed and direction
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test and checkout of these elements into the Launch System is excluded.
D.4.4.5 Ready Magazine. The structure or compartment for storing ammunition or explosives in a ready- for-use condition or position (e.g., the part of a gun or firearm that holds the ammunition ready for chambering and feed mechanisms for placing the ammunition in a position ready for chambering).
D.4.4.6 Adapter Kits. The equipment (hardware/software) for adapting the launch system to particular applications (e.g., vehicle adapter kits for adaptation to different aircraft models, kits for backpacking, etc.).
NOTE 1: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test and checkout of these elements into the Launch System is excluded.
D.4.4.7 Launch System Software Release 1…n. All launch system software not associated with a specific Level 3 or 4 element.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.4.8 Other Launch systems 1…n (Specify). This element comprises the complex of equipment, not included in the above Level 4 elements, that is unanticipated at the time of issuance of this appendix due to the evolution of technology but necessary to complete this Level 3 element.
NOTE: If lower level information can be collected, use the structure and definitions in Appendix B, Electronic/ Systems. NOTE 2: All effort directly associated with the remaining Level 3 WBS elements and the integration, assembly, test, and checkout of these elements into the Launch System is excluded.
D.4.5 Ordnance System Software Release 1…n. All Ordnance System software not associated with a specific Level 2, Level 3 or Level 4 element.
NOTE: Refer to Appendix B, Electronic Systems for further breakout and definitions for Software.
D.4.6 Ordnance System Integration Assembly Test and Checkout. This element includes all effort of technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, interconnect harnessing and software required for the integration, assembly and checkout of the above Level 2 elements into their Level 1 element, Ordnance System.
D.4.7 Common WBS Elements. Definitions for Common WBS elements applicable to the Ordnance System, and all other defense materiel items, are listed in Appendix L: Common Elements, Work Breakdown Structure and Definitions.